Ottawa’s light-rail transit system faces a significant test this week in the lead up to the opening of the O-Train East Extension, with 23 trains running on the line for the first time. Starting this week, OC Transpo and Rideau Transit Maintenance are “exercising the entire system” by running trains along the full O-Train Line 1 between Tunney’s Pasture and Trim Station. OC Transpo general manager Rick Leary says it’s part of a staged approach to the eventual opening of O-Train Line 1 between Blair Station and Trim Station. “This will be the first time that Rideau Transit Maintenance (RTM) will launch 23 trains for service, running about every four and a half minutes,” Leary said in a memo to council earlier this month. “This allows us to test the vehicles, schedules, and staffing assignments, and is the next step in the preparation for Pre-Trial Running.” Customers will be able to ride the O-Train between Tunney’s Pasture and Blair stations but will need to disembark the train at Blair Station. Beacon Hill-Cyrville Coun. Tim Tierney told CTV News Ottawa on Sunday that the pre-testing is generating “a lot of excitement. “With all the double-trains rolling around right now, seems it’s going quite well,” Tierney said.” “They will come back to committee and council and tell us how it’s going? The report back and give us a definitive timeline when they’re going to start that 21-day clock. The very important 21-day clock. I anticipate it will probably be sooner than later.” Testing on the full line is expected to continue for a “few weeks,” according to Leary. “While all system elements are exercised. There may be times when this testing identifies an issue that RTM or EWC needs to address, and this may impact train operations between Blair and Trim stations,” Leary said in a memo on Nov. 18. “This is a normal part of the testing process. Our priority is maintaining the existing O-Train Line 1 service for our customers.” Tierney insists the O-Train East Extension will be worth the wait for commuters in the east end. “When this train turns on, it’s going to stay on,” Tierney said. “Unlike what happened in Stage Oe, and that is an important message for people that actually want to get on the train and know they have a reliable way to get downtown. So, you know what? A little more pain is going to have a lot more gain at the end of the day.” East-end councillor optimistic Orléans East-Cumberland Coun. Matt Luloff says he’s cautiously optimistic over the new testing milestone but says residents who have endured years of construction and delays have reason to be frustrated. “This is a good step in the right direction, but I still remain cautiously optimistic at this point,” says Luloff. “We’ve been waiting for this for a very, very long time,” Luloff said. “My residents have been put through hell when it comes to construction, when it comes to these delays.” Luloff says he supports OC Transpo’s approach to testing, arguing safety and reliability should take priority over meeting a promised opening date. “I don’t think you can over-test with a system like this,” he said, comparing the process to waiting through multiple stages in a hospital before finally seeing a doctor. He says he would rather see the agency take more time to get it right than rush the extension into service. “For me, it’s about transparency and ensuring that people are aware of what’s going on,” he says. Luloff also says the launch must be accompanied by improvements to OC Transpo’s bus network, including more convenient routes and shorter walking distances for passengers. “We’re going to need to ensure that buses are showing up on time, that the routes make sense, that the routes are servicing major collectors, so that people only have to walk to the end of their street to get on a bus. We need to make this convenient again. OC Transpo only has one shot at a good first impression.” Luloff acknowledges residents are frustrated watching trains travel back and forth without passengers. “They just want the system open, and they want it working properly,” he said. For passengers, the full line testing changes very little for their commute, since they will still need to get off at Blair. Sarah Mawhinney says, “I’ve been doing that same commute for the past four years. I’m in my master’s now, and I did my four years of undergraduate at U of O, so it was pretty normal for me. It did feel weird to not hear the Blair as the last stop kind of announcement. I’ve been hearing the Blair is the last stop announcement for a long, long time.” Gordon Webb isn’t ready to trust the system yet. “I’ve always learned to be cautious when it comes to the old train and announcements and that. I guess I’m just wait and see.” Meanwhile, passengers like Casey Wong says, “it is encouraging to see (the trains) come out this far.” East Extension to close for a week While O-Train Line 1 will run on the full Tunney’s Pasture to Trim Station line this week, the East Extension will close the week of Nov. 29. Leary said the contractor, East-West Connectors, asked that trains not operate between Blair and Trim stations for a week for “advance upgrades to track infrastructure, which will help increase system reliability.” “Once the system readiness is validated, we will be ready to begin Pre-Trial Running,” Leary said. “We will provide an update to Council when we have confirmed the timing for testing activities in December, including when we are ready to begin Trial Running and details on a technical briefing.” Leary said Pre-Trial Running will last at least a week before the 21-day trial running period begins. With files from CTV News Ottawa’s Leah Larocque