The Alberta Utilities Commission has rejected an application to build a mega data centre in Olds. Back in January, Synapse Data Center and the town announced plans for a $10-billion project on the east side of the southern Alberta town. Backers want to build a 1.4-gigawatt facility powered by natural gas turbines. Some residents expressed concern about noise, as well as environmental and health issues. On Friday, the commission posted a decision saying the proposal was missing information and there was a lack of public consultation. “As a result, the commission has determined that it will not continue to process the application,” the commission said. “For clarity, the commission is not making a determination on the merits of the application at this time; it is assessing whether the information provided meets its requirements.” The commission also said the decision is “without prejudice to Synapse reapplying in the future.” In a statement to CTV News, Synapse said it’s reviewing the decision. Synapse said it will seek additional public feedback, with an aim to reapply. Synapse said the project is “designed to be a 100-year fixture in the Olds community.” “It is critical that we work closely with both regulators and our neighbours to ensure the project’s foundation is built on transparency and trust,” said Jason Van Gaal, Synapse CEO. “We have taken the AUC’s guidance and our community’s feedback to heart.” Synapse said it is launching synapsedatacenter.com/we-are-listening/ as “a first step in facilitating our long-term dialogue.”